Overview

Traffic signal retrofits for Flashing Yellow Arrow (FYA) signal operations at four Hwy 212 interchanges involving ten (10) traffic signal intersections.  See map of the locations where these are at: Hwy 10 (Engler Blvd); Hwy 41 (Chestnut St.), Hwy 17 (Powers Blvd); and Hwy 101 (Great Plains Blvd.). While not part of this project, FYA is being planned for the Jonathan Carver Parkway/ Hwy 212 Interchange as part the Jonathan Carver Parkway Reconstruction Project with the City of Carver.

Description

As part of a MnDOT grant program called the Local Partnership Program, Carver County is partnering with the MnDOT and the City of Chanhassen to add Flashing Yellow Arrow signals at four key Hwy 212 Interchanges in Carver County.   

Work is mostly limited to adding new loops in the pavement on the left turn lanes on the mainline highways, along with new 4-section signal heads on these left turn lanes to show the flashing yellow arrow signal.  Some other related traffic signal equipment is being updated as part of the project as well. Fairly minor work, but some construction traffic impacts are expected  while this work is being done.

Goals & Objectives

Modernize traffic signals at key locations. Provide more flexible traffic signal operations, reduce delays and increase safety as much possible.

Current Traffic Impacts

See Below and stay tuned for updates

What to Expect

The contractor and project partners will begin work in early April through July/August, 2020, weather and conditions permitting. Some lane closures and traffic control will be in place at various project locations. Go slow and be careful of lane assignments and construction workers.

Detour Routes

No detour routes necessary. Work will be performed under traffic. There will be lane closures as needed.

See map of the locations where FYA signals are being added at Hwy 10 (Engler Blvd); Hwy 41 (Chestnut St.); Hwy 17 (Powers Blvd); and Hwy 101 (Great Plains Blvd.).

Anticipated Project Schedule

Visit the Construction & Closures App to view more information

The Project Schedule is anticipated to follow the each location as noted below;

Beginning Tuesday, May 5th:

System A & B: Hwy 10 at Hwy 212 - west bound on Hwy 10: left turn lane and left through lane

System C: Hwy 41 at Canyon Rd - north and south bound left turn lanes

System D & E: Hwy 41 at Hwy 212 - west bound left turn lane and left through lane

System F & G:  Hwy 17 at Hwy 212 - south bound on Hwy 17 at 212: eastbound left turn lane and left through lane

System H:  Hwy 101 at Hwy 18

System I &J: Hwy 101 at Hwy 212

Reports & Documents

More info on Flashing Yellow Arrow signal operations is noted here at: http://www.dot.state.mn.us/trafficeng/signals/flashingyellowarrow.html

Free viewers are required for some of the attached documents.